Good morning. Following are corrections to Wednesday afternoon’s email. Please accept my apologies for the misunderstanding and for any inconvenience the prior email may have caused. Following are construction updates for the next two weeks for the Allandale Storm Drain Improvements Project.
Completions Prior Week:
- Completed three inlets on White Horse.
- Began water line on Nasco
Rain Days: Friday, February 3 and Saturday, February 4. The schedule below is NOT taking into account additional rain days, although current weather reports suggest rain on Thursday and Friday of this week.
Continue reading "Corrections: Allandale Construction Update" »
Following are construction updates for the next two weeks for the Allandale Storm Drain Improvements Project.
Completions Prior Week:
- Begun work on inlets on White Horse.
- Storm drain inspections on the first 1000 feet of Bull Creek have been completed
- Water lines on Nasco
Rain Days: Friday, February 3 and Saturday, February 4. The schedule below is NOT taking into account additional rain days, although current weather reports suggest rain on Thursday and Friday of this week.
Continue reading "Storm Drainage Project Update - 02.08.12" »
Good afternoon! Following are construction updates for the next two weeks for the Allandale Storm Drain Improvements Project.
Completions Prior Week:
Installed fire hydrant between Northland and 2222 on Bull Creek
Installed fire hydrant between White Rock and 2222 on Bull Creek
Installed inlet on the corner of Bull Creek and White Rock
Installed 6 sewer services on Nasco
Upcoming:
Please note: The original construction schedule for this week showed work beginning Monday, January 9. Due to rain, work has been delayed at least one day. The dates below reflect a single “rain day”. If the rain continues into Tuesday, January 10, each date below will slip an additional day.
Bull Creek
Inlet Installation on Bull Creek will require full closure on Bull Creek immediately North of 2222 from Tuesday, January 10 through Friday, January 13.
Additional inlet installations will occur on Bull Creek on Monday, January 16 through Wednesday, January 18. Flaggers will be operating on Bull Creek between White Rock and White Horse on these dates.
Sewer service work from 6001 Bull Creek to 6007 Bull Creek will require a flagger operation from Tuesday, January 10 through Thursday, January 12.
Sewer line will be tested on Bull Creek from Tuesday, January 17 through Thursday, January 19. No street closures or reductions are associated with this work.
Note that while the sewer lines are being installed and lines tested, there may be some interruption to regular services. If this is the case, a representative will notify you. On those possible dates, we would ask that you not take hot showers, etc between 9:00 a.m. to 4:00 p.m.
Continue reading "City of Austin Public Works: Allandale Storm Drain Improvements CONSTRUCTION UPDATE" »
Completed:
All water lines on Northland and Bull Creek are complete
Two fire hydrants were put in, active water line in way.
Inlets north of White Rock on Bull Creek
General
Letters regarding inlet or fire hydrant installations will be hand delivered on Thursday, December 22 to those addresses where the inlets will be installed.
The crews are still installing inlets and should be finished with inlet work by the end of February. Three inlets remain on White Horse. Seven inlets remain on Nasco.
Construction crews will not work between December 23-January 3rd in observance of the holidays.
Continue reading "Allandale Neighborhood- Construction Update" »
The following are answers from the City to the questions that came up in last weeks public meeting held at the Northwest Recreation Center on the Allandale Storm Drain Project.
Allandale Public Information Meeting
December 1, 2011
Northwest Recreation Center
Questions and Answers
What options are there to complete the project faster?
We are compressing the contractor’s work schedule by allowing them to work in two areas simultaneously, from Shoal Creek heading north and from Allandale north. The project team is targeting mid-April for completion of the work.
How is the project affecting Austin Memorial Park Cemetery?
We are currently investigating any possible impacts the project may have on the Austin Memorial Park Cemetery. Additional information will follow.
What is the schedule now? Can you tell us what work will be done and approximate time these tasks will begin? How long will they last?
The contractor’s 2 week look-ahead schedule is attached. This schedule is currently under review by the City and may be modified. Detailed descriptions of the work will be provided in the weekly email updates. Residents are also invited to attend the weekly Tuesday 5:30 pm meetings for more detailed discussions and questions.
How will the accelerated option work?
We’ll work from Shoal Creek heading northward and from Allandale northward. We will pave these two areas at the same time. This may start as early as January 3, 2012.
Continue reading "Answers to questions from Allandale Storm Drainage Project meeting" »